Traffic updates
Service Stream is committed to minimising disruptions and keeping you informed so you can plan your journey with confidence.
Stay up to date with the latest traffic conditions, planned maintenance and important works happening along Peninsula Link.
Peninsula Link Pavement Works staged schedule
| Stage | Location | Date (weather permitting) | Time | Traffic impacts | Status | Notification |
|---|---|---|---|---|---|---|
| 5A | Northbound between Old Moorooduc Road and Bungower Road | April 8 to June 8 | 24/7 | Carriageway CLOSED – Northbound between Moorooduc Hwy and Bungower Rd – all traffic diverted off the freeway at Moorooduc Highway. Works to rebuild the pavement structure. Due to expected low temperature over winter, the road will reopen without the final surface layer. Speeds will be 100kph. | Planned | View |
| 5B | Northbound between Moorooduc Highway and Bungower Road | TBA, Likely to be December 1 to December 18 | 24/7 | Carriageway CLOSED – Northbound between Moorooduc Hwy and Bungower Rd – all traffic diverted off the freeway at Moorooduc Highway. Placement of final pavement surface and line marking. | Planned | |
| 1 | Southbound between Frankston-Flinders Road and Bungower Road | Feb 1 2026 | 24/7 | Works completed and reopened to traffic | Works completed | |
| 2 | Southbound between Bungower Road and Old Moorooduc Road | March 6 2026 | 24/7 | Works completed and reopened to traffic | Works completed | |
| 3 | Northbound between Bungower Road and Frankston-Flinders Road | March 10 to March 21 | 24/7 | Works completed and reopened to traffic | Works completed | |
| 4 | Northbound between the Nepean Highway and Old Moorooduc Road | March 23 to March 27 | 24/7 | Works completed and reopened to traffic | Works completed | |
Major reconstruction works currently underway
Peninsula Link Pavement Works
Major works are being carried out along 14 kilometres of the southern sections of the Peninsula Link. Delivered in stages, the works will replace the road to keep the connection between the Mornington Peninsula and Melbourne safe and reliable.
These works are built into the Peninsula Link contract with the State of Victoria and are not an additional cost to taxpayers.
Impacts, road closures and delays
Some lanes and ramps will be closed while works are underway. Reduced speed limits are likely throughout the work period, even when road workers aren't visible because the physical condition of the road has changed, creating hazards that are not always obvious to drivers.
Delays are likely and we urge motorists to allow plenty of extra time if travelling on Peninsula Link.
To subscribe to the email distribution list for this project, please contact peninsulalink@servicestream.com.au
Upcoming closures
Stage 2 surfacing works commenced at 7pm on Thursday, 19 February and will continue until 6am Friday, 6 March.
Weather permitting, these works are scheduled for completion ahead of the Labour Day long weekend, with all lanes reopened and the speed limit restored to 100km per hour.
Stage 3 works are scheduled to commence 10 March 2026. Further details on all roadwork stages, including maps, can be found in the Works Schedule table above.
Please note that all works are weather dependent and schedules may change if conditions are unsuitable.
Frequently Asked Questions
Click here to view frequently asked questions on these pavement works.
Incident and emergency closure notifications
| Date | Time | Location | Activity | Notification |
|---|---|---|---|---|
Upcoming road closures for maintenance
| Date | Time | Location | Activity | Notification |
|---|---|---|---|---|
| 17th March - 10th April | 6AM - 6PM | Eastlink Entry Ramp - Northbound | Maintenance activities on bridge walls with single lane closures during work times. Delays expected. |