1. Home
  2. peninsula link
  3. Traffic updates

Traffic updates

Service Stream is committed to minimising disruptions and keeping you informed so you can plan your journey with confidence.

Stay up to date with the latest traffic conditions, planned maintenance and important works happening along Peninsula Link.

Peninsula Link Pavement Works staged schedule

Stage Location Date (weather permitting) Time Traffic impacts Status Notification
5B Northbound between Moorooduc Highway and Bungower Road TBA, Likely to be December 1 to December 18 24/7 Carriageway CLOSED – Northbound between Moorooduc Hwy and Bungower Rd – all traffic diverted off the freeway at Moorooduc Highway. Placement of final pavement surface and line marking. Planned
5A Northbound between Old Moorooduc Road and Bungower Road April 8 to June 8 24/7 Works completed and reopened to traffic Works completed
1 Southbound between Frankston-Flinders Road and Bungower Road Feb 1 2026 24/7 Works completed and reopened to traffic Works completed
2 Southbound between Bungower Road and Old Moorooduc Road March 6 2026 24/7 Works completed and reopened to traffic Works completed
3 Northbound between Bungower Road and Frankston-Flinders Road March 10 to March 21 24/7 Works completed and reopened to traffic Works completed
4 Northbound between the Nepean Highway and Old Moorooduc Road March 23 to March 27 24/7 Works completed and reopened to traffic Works completed

Major reconstruction works currently underway

Peninsula Link Pavement Works

Major works are being carried out along 14 kilometers of the southern sections of the Peninsula Link. Delivered in stages, the works will replace the road to keep the connection between the Mornington Peninsula and Melbourne safe and reliable. 

These works are built into the Peninsula Link contract with the State of Victoria and are not an additional cost to taxpayers.

Impacts, road closures and delays

Some lanes and ramps will be closed while works are underway. Reduced speed limits are likely throughout the work period, even when road workers aren't visible because the physical condition of the road has changed, creating hazards that are not always obvious to drivers. 

Delays are likely and we urge motorists to allow plenty of extra time if travelling on Peninsula Link. 

To subscribe to the email distribution list for this project, please contact  peninsulalink@servicestream.com.au

Planned closures

Northbound carriageway closure – reopened Thursday 4 June 2026

The Peninsula Link northbound carriageway closure between Moorooduc Highway and Bungower Road has now reopened.

The closure was originally scheduled to remain in place until Monday 8 June 2026 but was completed early and the road reopened to traffic on Thursday 4 June 2026, ahead of the long weekend.

Crews have now completed final activities, including pavement works, line marking and safety checks, to safely reopen the road.

Northbound entry ramps from Mornington-Tyabb Road and the Moorooduc Highway, as well as the exit ramp to Bungower Road, have also reopened with the northbound carriageway.

The northbound service centers have remained open throughout the works.

Motorists are advised to continue to take care and following signage.

Northbound closure planned for December 2026

Further closures of the northbound carriageway will be required in December 2026 to lay the final surface. We will notify the community in advance of these works.

Travel advice

We acknowledge delays can be frustrating and we would like to thank the community for your patience.

Please continue to allow extra travel time and follow signed detours. 

All dates are subject to weather and site conditions.

Frequently Asked Questions

Click here to view frequently asked questions on these pavement works. 

Incident and emergency closure notifications

Date Time Location Activity Notification

Upcoming road closures for maintenance

Date Time Location Activity Notification
17th March - 14th June 6AM - 6PM Eastlink Entry Ramp - Northbound Maintenance activities on bridge walls with single lane closures during work times. Delays expected.
10th June - 12th June 2026 8PM to 5AM Cranbourne Road Entry Ramp - Outbound. Entry ramp will be closed for removal of cladding on the Willow Road Pedestrian bridge.
3rd July - 5th July 2026 8PM to 5AM Cranbourne Road Entry Ramp - Outbound Entry ramp will be closed for the installation of new cladding on the Willow Road Pedestrian Bridge.

Related pages