1. Home
  2. peninsula link
  3. Peninsula Link Pavement works

Peninsula Link Pavement works

Frequently Asked Questions

Who is responsible for Peninsula Link?

Peninsula Link is a public-private partnership (PPP). The State of Victoria engaged the Southern Way consortium to design, build, finance, operate and maintain the freeway for 25 years. 

The freeway’s operations and maintenance requirements sit within the PPP structure. Service Stream, on behalf of Southern Way, holds a 25-year contract to operate and maintain the road, and to facilitate major refurbishments required to meet the contracts performance standards. 

Are the major pavement works government funded?

No. There is no additional cost to the taxpayer or the State of Victoria for these major pavement works. 

Why are these major works needed?

We’re rebuilding the road from the ground up to ensure the road can meet the demands of the growing population and provide a smoother, more enjoyable journey for all road users for decades to come. 

These works will be carried out along 14 kilometres of the southern sections of the Peninsula Link. The works will be delivered in staged sections and include all pavement layers including the top surface layer.

How long will these works take?

The Peninsula Link Pavement Works are advancing at significant pace to minimise the duration of impacts experienced by motorists and local residents. Works initially commenced in July 2025. All stages are expected to be complete by 30th March 2027 depending on weather conditions. 

The full works schedule can be found here.

Why does the weather impact the works?

Like all road projects, weather conditions can impact the schedule and timelines may need adjusting. Dry and warm weather conditions are required to properly place the pavement layers; this is particularly important for the top asphalt layer. 

Why are speed limits reduced?

Reduced speed limits are likely throughout the work period to ensure safety for all road users. These reduced limits are required, even when road workers aren't visible, because the physical condition of the road has changed, creating hazards that are not always obvious to drivers.

How are you managing the impacts from these major works?

At times, some lanes and ramps will be closed while works are underway. Delays are likely and we encourage motorist to check before you travel and allow extra time. For closure details and maps, visit our Traffic Updates page here.

Have there been any safety incidents recorded on site?

Safety is our number one priority. We have comprehensive safety procedures in place in compliance with our OH&S obligations. There have been no reportable safety incidents to date on the Peninsula Link Pavement Works.

We heard that incorrect materials were used in the most recent resurfacing works and the road needs to be urgently ripped up, is that correct?

No, there is no need to rip up or rectify recent works due to incorrect materials or any other reason. The Peninsula Link Pavement works must be undertaken in three steps: removal of old pavement, placement of the new underlying structural pavement and placement of the surfacing layer. Works are progressing as expected. 

Why have the major works been delayed until February 2027?

The works schedule has been revised, with major northbound carriageway works now scheduled to recommence in February 2027, so as not to cause disruptions during the summer school holiday period.

Under the revised schedule, the next major northbound carriageway closure will not take place over the Melbourne Cup long weekend or the busy December and summer school holiday period. Minor maintenance works will continue in the meantime, with short-duration overnight ramp and lane closures rather than full main carriageway closures.

Has maintenance work stopped until February?

Minor maintenance works will continue between now and mid-December 2026. These will be undertaken overnight and will be of limited duration.

Motorists can expect some overnight ramp closures and lane closures in both directions while these works are carried out.

Is there a speed restriction on Peninsula Link?

The freeway will operate at 100 km/h wherever possible over the summer period.

Temporary lower speed limits may be required in response to inclement weather as the final layer of asphalt is not yet complete. Once the weather passes, the speed limit will return to 100 km/h.

Normal lowered speed limits will apply around emergency services, incidents and emergency maintenance works.

Motorists must always follow the posted speed limit, which may vary along the freeway depending on conditions.

Will the minor works require the freeway to close?

No. The full closure of either main carriageway is not required for these minor works. However, some entry or exit ramps will close overnight, and lane closures will be required.

Motorists should follow road signage and allow additional travel time when these restrictions are in place.

Will the February works require a carriageway closure, and for how long?

Yes. The major works on the northbound carriageway (also known as the inbound direction) will require a full closure.

The closure dates, duration and detour route will be communicated closer to the start of works so motorists can plan their journeys.

Where can motorists find further information?

Updates will be published on the Peninsula Link website, including closure dates and detour arrangements for the major works commencing in February 2027.

Motorists should also follow road signage for traffic conditions and restrictions when travelling.